Delivered under pressure.

Every engagement is different. Below are a selection of real projects where B&W INFRA delivered measurable outcomes for clients facing complex M&E challenges — from emergency response to strategic advisory.

Client identities are anonymised to protect commercial confidentiality.

Sector
Duration
M&E AdvisoryHealthcare· 6 Weeks

Critical Infrastructure Failure — Rapid Response & Recovery

A major NHS Trust experienced a cascading electrical infrastructure failure across two acute hospital buildings, threatening patient safety and clinical operations.

48 hrs

Mobilisation time from initial call

Zero

Clinical procedures disrupted during reinstatement

£1.2M

Capital investment prioritised via risk register

HTM 06-01

Full compliance achieved on all works

Compliance AuditCommercial Real Estate· 4 Weeks

Pre-Handback M&E Audit — New-Build Commercial Development

A regional developer engaged B&W INFRA to conduct a comprehensive M&E compliance audit prior to practical completion of a £28M Grade-A commercial office development.

47

Non-conformances identified and documented

£340K

Estimated remediation value protected via defect schedule

100%

Commissioning records verified before handover

On time

Tenant handover achieved to programme

Project ManagementPublic Sector / FM· 12 Weeks

FM Mobilisation — Mechanical Systems Overhaul, Multi-Site Estate

A local authority with a diverse 34-building estate engaged B&W INFRA to manage an emergency procurement and mobilisation of mechanical systems maintenance following incumbent FM contractor insolvency.

34

Buildings stabilised with compliant cover

14 days

Interim FM provider appointed

Zero

Statutory inspection failures during transition

PCR 2015

Full procurement compliance maintained

Design ReviewTechnology / Data Centres· 8 Weeks

HVAC Design Challenge — High-Density Data Centre Fit-Out

A technology firm retained B&W INFRA to provide independent technical review and value engineering of mechanical design proposals for a new 2MW high-density data centre fit-out within an existing warehouse shell.

£480K

Capital cost reduction achieved

1.38

PUE achieved — below 1.4 target

N+1

Full resilience maintained across all systems

38%

Budget overrun eliminated